New Contract for I-580 Freeway: Project Resumes

The State of Nevada awards a $393 million contract to Fisher Gravel & Sand Company as prime contractor to complete the
I-580 Freeway Extension Project. The contract was approved to be awarded by the State Board of Transportation on November 6, 2006. Notice to Proceed has been scheduled for December 2006. The Nevada Department of Transportation is looking forward to working with Fisher Gravel and Sand Company, and their bridge subcontractor, C.C. Myers, to complete the project and have it open to traffic in mid 2011.

Bid Item Summary - October 5

The following file is the updated bid item summary for Contract 3292 in Excel format. The items and quantities are current through Supplemental No. 7, issued October, 2006. The bid item summary provided here is for the convenience of bidders and does not replace the proposal contained in the special provisions. 3292 Bid Item Summary 061005

Pre-Bid Meeting #2- September 26

Read about the September 26 pre-bid meeting in the following PDF files:
I580 PreBid_No2_Agenda_and Roster
3292_Staffing_Matrix_092506

Bid Item Summary - September 18

The following file is the updated bid item summary for Contract 3292 in Excel format. The items and quantities are current through Supplemental No. 6, issued September 18, 2006. The bid item summary will be updated any time a supplemental is distributed which affects the bid items or quantities. The bid item summary provided here is for the convenience of bidders and does not replace the proposal contained in the special provisions. 3292 Bid Item Summary 060918

New Bid Opening Date

NDOT will extend the bid date to October 12, 2006 in a Supplemental Notice to be issued on or around September 7, 2006. If you have any questions, please contact Todd Montgomery at 775-888-7318.

Construction Schedule Summary

The following file is a construction schedule summary for Contract 3292. The construction schedule provided here is for the convenience of the bidder and will require agreement to the disclaimer before downloading. 3292 Schedule 060824 Overall and Galena Creek.

Bid Item Summary - August 24

The following file is the updated bid item summary for Contract 3292 in Excel format. The items and quantities are current through Supplemental No. 4, issued August 24, 2006. The bid item summary will be updated any time a supplemental is distributed which affects the bid items or quantities. The bid item summary provided here is for the convenience of bidders and does not replace the proposal contained in the special provisions. 3292 Bid Item Summary 060824

August 11th Mandatory Pre-Bid Meeting

On August 11, 2006, NDOT held a mandatory pre-bid meeting for the I-580 Project. The links below provide information that was presented at that meeting:

Bidders will be required to obtain two bonds for Contract 3292.  One bond will be for the work completed during the allotted number of working days established in the Contract.  The second bond will be for the plant establishment work that will continue past the end of construction date.  Additional information regarding this will be contained in Supplemental No. 4 issued on or around August 24, 2006.
 
For other issues raised during the pre-bid meeting that did not receive an adequate response, please submit an electronic request for information.

June 28th Contractor Outreach Meeting

On June 28th, 2006 the I-580 Freeway Extension Project held a Contractor Outreach Meeting. If you are interested, the links below provide you with the information that was presented at the meeting:

In addition, the following bridge contractors are prequalified to construct major bridges for Contract 3292:

  • C.C. Myers, Inc.
  • Granite Construction Company/ FCI
  • Kiewit Western Company
  • Traylor Brothers, Inc.

Bid Item Summary - July 20th

The following file is a bid item summary for Contract 3292 in Excel format. The items and quantities are current through Supplemental No. 1, issued July 20, 2006. The bid item summary will be updated any time a supplemental is distributed which affects the bid items or quantities. The bid item summary provided here is for the convenience of bidders and does not replace the proposal contained in the special provisions. 3292 Bid Item Summary 060720.

 

JUNE 2006 & BEYOND

Updated Construction Advertising Dates Announcement
(posted 06/20/2006)

Advertising dates are for remaining I-580 construction are listed below. Click links for complete information on meeting times, dates, and locations.

  • Mandatory Pre-Bid Meeting: August 11, 2006
  • Note date change below:
  • Bids Due: October 12, 2006
  • Estimated Notice to Proceed: December 2006

These documents are Adobe Acrobat or "PDF" files. They can be read using the Adobe Acrobat Reader — a free program available for all computer platforms. Click the graphic to the left to download.

*Additional details will be posted here as they are available.

Contractor’s questions call: Todd Montgomery, NDOT Project Manager 775.888.7318