What's New?What's New Icon

News Archive 

One Month Preview of Construction Activities

Southbound Arch at Galena Creek Bridge Begins to Take Shape
Galena Creek Fill Complete
Work in Full Swing at South End of Project
I-580 Public Tours Restricted
I-580 Project Spring 08 Newsletter
Project Schedule


One Month Preview of Construction Activities — Updated Monthly

Type of Activity

Date

Area Affected

Details/Notes

Traffic

August

 

Mt. Rose Interchange

This is the main access for the project on the north end. Construction equipment and materials are moving onto and off the project from I-580 and the Mt. Rose Highway.

Traffic control measures may be in place on a periodic basis for construction activities along the Mt. Rose Highway.

 

   

Parker Ranch Road

This is the main access for the project on the south end. Construction equipment and materials are moving onto and off the project at the US-395 - Parker Ranch intersection in Washoe Valley.

 

   

Bowers Mansion Road

 

Some traffic control measures will be in place for construction equipment and materials moving into and out of the project, along with temporary shoulder closures.

Lane Closure

August

 

No lanes closures are scheduled.

Noise

August

Mt. Rose Interchange
and areas just to the south

Light to medium noise due to earth moving and grading operations, construction of Galena Forest Bridge, and construction of Mt. Rose culvert.

 

   

Steamboat south to just north of Pleasant Valley

 

Light to medium noise due to grading operations, construction of Steamboat Hills and Pleasant Valley Bridges, and construction of retaining walls.

 

   

Pleasant Valley

 

Medium noise due to grading operations and construction of retaining walls.

   

Galena Creek Bridge

 

Medium to Heavy noise due to construction of Galena Creek Bridge falsework and concrete pours.

   

Galena Creek Bridge to Browns Creek Bridge

 

Medium noise due to grading operations between Galena Creek and Browns Creek bridges.

   

Browns Creek Bridge to Parker Ranch Road

 

Light to medium noise due to grading operations and installation of pipes.

   

Parker Ranch Road to Bowers Mansion Road

 

Light to medium noise due to culvert construction and grading operations.

 

Construction

August

Processing Aggregates

Concrete and asphalt aggregate operations continue near the Galena Forest Bridge.

 

   

Grading

 

Grading operations continue along the entire length of the project in select locations including:

  • Mt. Rose Highway and areas to the south
  • All areas of Pleasant Valley
  • Between Galena Creek and Browns Creek Bridges
  • North of Bowers Mansion Road.
   

Crushing

 

Crushing operations continue on the north end of Pleasant Valley.

   

Bridges

 

Mt. Rose Highway Bridge
No work at this time.

Galena Forest Bridge
Columns are complete. Finishing abutments and backfilling around column footings.

Steamboat Hills Bridge
Superstructure construction continuing with placement of reinforcing steel and starting concrete pours.

Pleasant Valley Bridge Superstructure construction continuing with placement of reinforcing steel and concrete pours.

Galena Creek Bridge Continuing to place falsework along entire length of bridge. Continuing to build the Northbound Pier 2 and 3 thrust blocks along with column at Pier 2.

St. James Bridge
Painting bridge.

Browns Creek Bridge
No work at this time.

Parker Ranch Road Bridge
No work at this time.

Bowers Mansion Road Bridge
No work at this time.

 

   

Retaining Walls

 

Continuing with construction of retaining walls between Pleasant Valley and Steamboat Hills Bridges. Start excavations for retaining walls in Pleasant Valley. 

   

Drainage

 

Continuing to install pipes from Steamboat Hills Bridge to Pleasant Valley. New pipe installations will start north of Galena Creek Bridge, the area north of Parker Ranch Road, and around the Bowers Mansion Road.

   

Steamboat Creek Culvert

 

Finishing construction of Steamboat Creek Culvert near the Mt. Rose Interchange.

   

Mt. Rose Culvert

Placing reinforcing steel for Mt. Rose Culvert and pouring concrete. Culvert located in the Mt. Rose Interchange.

   

Winters Creek Culvert

Continuing to place reinforcing steel and pour concrete for Winters Creek Culvert and channel located just north of Bowers Mansion Road.

   

Other Work

 

None.

 

 

Southbound Arch at Galena Creek Bridge Begins to Take Shape

The falsework for the southbound arch of the Galena Creek Bridge is under construction and visible from US 395. Approximately half of the falsework is in place and the future arch span can already be seen by local residents and passing motorists.

Once complete, there will be two (2) arches, each supporting the southbound and northbound bridge decks respectively. The Galena Creek bridge will measure 1700 in length with an arch span of 690 feet. The bridge deck will stand 295 feet above the base of the creek.

Concrete pours for the arch are scheduled to begin the first week of August.

Galena Creek Fill Complete

The Galena Creek fill has been completed and is now being graded to create a stable work surface for crews and equipment. Bridge contractor, CC Myers, has begun drilling for the falsework foundation piles and will soon begin erecting falsework that will support the Galena Creek Bridge construction.

The fill measures 390 feet wide at its base, tapers to 200 feet wide at the top, and is approximately 120 feet high. 380,000 cubic yards of material were moved during the construction of the fill. A 44-foot diameter culvert runs through the base to preserve the natural course of Galena Creek and to provide enough additional capacity for potential increased flows during major storm events.
The fill is slated to be removed and the affected hillsides restored once the project is complete.

Work in Full Swing at South End of Project

Work is now in full swing at the south end of the I-580 Freeway Extension Project near the intersection of Bower's Mansion Road and US 395. Crews have removed some trees and have begun the removal and stockpiling of topsoil. The removal of noxious weeds is in progress and crews have started the construction of drainage pipes and culverts in the area. Much of this activity is visible from US 395.

Continued earthwork to support the roadway bed has begun south of Galena Creek between Browns Creek and Parker Ranch Road.

 

I-580 Public Tours Restricted

NDOT has announced it will restrict public tours for the I-580 Freeway Extension Project. The project tours were well received and typically booked months in advance during the tour season. However, with an eye toward fiscal responsibility as well as public safety, project officials decided that restricting the tours until work zone access is increased and made safer would be in the public's and workers' best interests.

"As the project moves into the next phases of construction, increased activity on the site will make it difficult to ensure that tour participants have a safe and enjoyable experience," says NDOT Project Manager, Todd Montgomery, P.E. "Also, in light of our State's current budget concerns, we feel that cutting costs in this non-essential area is a fiscally responsible and appropriate course of action."

Group and organizational tours may still be available on a limited basis subject to construction activity, weather conditions, and staff availability. Please contact the NDOT Public Information Office at 775-888-7000 for additional information.

NDOT will continue to update their project website and publish a project newsletter in an effort to keep the public informed on the project's progress.

Hours of Construction

NDOT is working hard to make progress on the Freeway Extension Project, with as little impact to area residents as possible. This includes keeping the project on schedule and moving forward as rapid as possible. The contractor is generally limited to working on the Galena Creek Bridge and near residential areas from 7:00am to 9:00pm Monday through Friday and, if the contractor chooses, 9:00am to 9:00pm on Saturday and Sunday. Few special situations, such as large pours of concrete, may require extended work hours. These situations will be individually approved by NDOT and noticed on the website well in advance. Additionally, residents within 3 miles (5km) will be noticed 2 weeks in advance of large concrete pours outside of the normal working hours. Project lane closures are also not permitted on state and national holidays, as well as during the local "Hot August Nights" and "Street Vibrations" events.